A U.S. Department of Energy emergency order directing PJM Interconnection to use additional generating resources has prompted a Michigan solar-mounting manufacturer to call for more power capacity before emergency measures become routine.
The order, dated Oct. 12, 2026, took effect Oct. 13-16. It authorizes specified power plants to operate as needed for reliability and allows backup generators at large facilities to help reduce grid demand during emergencies, according to a sponsored commentary by Terence Parker, a Michigan resident and Solar Mounts LLC team member.
Solar Mounts LLC describes itself as a Michigan-based designer and manufacturer of commercial- and utility-scale solar mounting systems. The company says the order does not mean blackouts are inevitable, but it highlights serious challenges for the electricity system and the need to add capacity before emergency steps become ordinary.
Capacity prices signal pressure
Parker points to PJM's capacity auctions as evidence of the difficulty in securing enough electricity for future demand. Prices reached $329.17 per megawatt-day for the 2026-2027 delivery year and $333.44 per megawatt-day for 2027-2028, with the later auction falling short of PJM's stated reliability requirement, the commentary says.
Capacity costs are only one part of electricity bills, but rising prices indicate growing pressure on consumers, according to the commentary. It argues that more power is needed before shortages force increasingly expensive emergency responses.
The October order permits designated generating units to exceed specified operating limits when necessary for reliability. It also authorizes PJM to direct backup generation at data centers and other large facilities, potentially including diesel generators as a last resort.
Solar Mounts says running fossil-fuel plants more often can increase emissions, depending on the units involved, while operating diesel generators can worsen local noise pollution and expose operators to high diesel prices. If such measures become more common, the company says, the question is why cleaner generation and storage are not coming online faster.
Winter outlook and generation options
The commentary cites NOAA's Oct. 15, 2026, winter outlook, which anticipates warmer-than-average conditions across much of the northern United States, including the Midwest, influenced by a strong El Niño. Seasonal forecasts cannot predict every period of extreme demand, Solar Mounts says, and aging infrastructure, maintenance, changing weather and growing electricity consumption reinforce the need for advance planning. Temporary authority to run additional fossil-fuel resources cannot replace long-term investment in generation, according to the company.
Solar Mounts argues that utility-scale solar, wind and battery storage can help meet demand on timelines many conventional generation projects cannot match. Suitable solar projects may be built within 18 months, depending on permitting, equipment and interconnection, while new nuclear facilities generally require substantially longer development periods, the commentary says.
Solar and wind reduce emissions when they displace electricity from fossil-fuel generators, and batteries store surplus electricity for periods of higher demand, according to the commentary. It notes that actual emissions benefits depend on which generators are displaced and when electricity is delivered.
The company also calls for faster interconnection reviews, saying qualified solar projects should not remain in queues for years because of avoidable administrative delays. Better coordination among PJM, utilities, regulators, developers and state governments, along with necessary transmission upgrades, would bring capacity online sooner, it says.
Land use and data centers
Solar Mounts acknowledges concerns about installing solar on productive farmland in rural Calhoun County. It says well-designed projects can include restoration plans that allow agricultural use to resume when leases end, and that solar leases can provide farmers with supplemental income when crop prices fail to keep pace with production costs. Agrivoltaic systems combine electricity generation with compatible crops or livestock, the commentary says, and thoughtful design and community engagement can balance renewable development with agricultural productivity and farmland preservation.
The company also points to parking lots, commercial properties, brownfields, landfills and other underutilized sites as places for solar. Solar carports can provide electricity, shade and weather protection, while community solar can expand access for people unable or unwilling to install their own panels, it says.
Data center demand, particularly in Virginia and other parts of PJM's territory, is adding pressure to an already constrained grid, according to the commentary. It says developers of new hyperscale facilities should show how they will secure adequate electricity and pay their fair share of supporting infrastructure through dedicated generation, renewable energy contracts, batteries, flexible demand and grid upgrades. Requiring every facility to build a gas-fired peaker plant is not necessarily the best answer, the company says, because gas turbines face equipment and supply-chain constraints and additional fossil-fuel generation carries emissions and operating costs. Existing facilities should also reduce peak demand, with energy efficiency remaining one of the most immediate options.
Solar Mounts concludes that Michigan and the wider PJM region should support faster approvals, better grid planning and a serious commitment to adding generation and storage before shortages worsen. Reliable electricity underpins the economy, jobs and daily life, it says, and repeated emergency orders, rising capacity costs and greater reliance on high-emission generation are not sound long-term strategies.