Who this checklist is for
I'm an office administrator for a 120-person company. I manage all custom manufacturing ordering—roughly $85,000 annually across 9 vendors. I report to both operations and finance. When I took over purchasing in 2020, I inherited a spreadsheet and a lot of guesswork. If you're buying aluminum machining service, stainless steel forgings, CNC mechanical parts, CNC machined products, aluminum connectors, or brass hose connector female parts, this checklist is for you. It's not a technical guide for machinists. It's the procurement process I use to keep engineering happy and finance off my back.
I have 8 steps. None of them are glamorous. All of them have saved me from a problem at least once.
Step 1: Define the part before you ask for pricing
This sounds obvious. It isn't. Most first RFQs I see go out with a sketch and a hope. Then the quotes come back all over the place because every supplier made different assumptions.
Before you contact anyone, collect:
- Material and grade—for example, 6061-T6 aluminum, 304 stainless, brass alloy.
- Quantity—single prototype, 10 pieces, 100 pieces, or more.
- Critical tolerances. If you don't know, ask engineering to mark them. Don't assume the shop will guess right.
- Surface finish and post-processing—anodize, powder coat, passivation, deburring.
- Thread standard for connectors. A brass hose connector female isn't just 'brass.' Is it NPT, BSP, metric, JIC? That changes everything.
Here's the thing: if your drawing doesn't specify tolerances, many shops default to ISO 2768-m. That's fine for a bracket. It's not fine for a mating connector. Put it on the drawing and call it out in the RFQ. If you're using GD&T, reference ASME Y14.5-2018 so everyone's reading the same symbols.
Step 2: Ask what the quote includes—not just the price
Most buyers focus on per-unit pricing and completely miss setup fees, revision costs, inspection, material certifications, and shipping. Those can add 30–50% to the total.
The question everyone asks is 'what's your best price?' The question they should ask is 'what's included in that price?'
I send this short list with every RFQ:
- Is setup charged separately?
- Are material certs included?
- Is first-article inspection included? If not, what does it cost?
- What's the lead time for the quoted quantity? Does it change if quantities shift?
- What's the packaging and shipping cost to our ZIP code?
- What happens if the parts fail inspection?
For CNC machined products and aluminum machining service, online quoting can be fast. Oshcut's instant quote is one I've used for prototypes because it forces some of these assumptions upfront. That said, you still need to read the fine print. Fast quotes don't remove the need for a checklist.
Step 3: Check whether the supplier is honest about scope
I have mixed feelings about 'one-stop' manufacturing. On one hand, fewer vendors means less admin work. On the other, I've watched a generalist promise a stainless steel forging, a CNC mechanical part, and a laser-cut bracket—then subcontract half of it and miss the deadline.
The vendor who said 'this isn't our strength—here's who does it better' earned my trust for everything else. That's the expertise boundary I look for. A good supplier knows what they're set up to do.
Ask directly: 'What's your core process? What do you run in-house versus outsource?' If they claim they do everything, ask for recent examples. If they're a CNC shop, they should be strong on CNC machined products, aluminum connectors, and maybe sheet metal. If you need a true stainless steel forging, don't assume a CNC shop forges it. Ask whether they machine forged blanks or source the forging.
I'd rather work with a specialist who knows their limits than a generalist who overpromises. At least, that's been my experience.
Step 4: Verify material traceability before you order
Everyone told me to verify material certs before approving. I only believed it after skipping that step once and receiving a batch of aluminum parts with no traceability. Engineering rejected them. We ate about $1,200 in scrap and delays.
Now I ask for:
- Mill certs or material test reports tied to the heat number.
- Country of origin if the part is for a regulated product.
- Certificates for any special processes—anodizing, plating, passivation.
For stainless steel forgings, material traceability matters even more. A forged part often goes through multiple hands: forging, heat treat, machining, finishing. If the cert chain breaks, you don't know what you have.
Step 5: Nail down connector specifications
Connectors are where small misunderstandings become big leaks. An aluminum connector or brass hose connector female part might look simple, but the details decide whether it seals or fails.
Before ordering, confirm:
- Thread type and size. NPT, BSPP, BSPT, metric, JIC, SAE—they're not interchangeable.
- Sealing method. O-ring, gasket, tapered thread, bonded seal?
- Pressure and temperature rating.
- Material compatibility with the fluid and environment.
- Inspection criteria. What makes the part acceptable? Go/no-go gauges? Visual? Dimensional report?
I'm not an engineer. What I mean is I don't pretend to know every thread standard. But I've learned to put the question in the RFQ and route the answer to engineering before we cut metal. That's cheaper than rework.
Step 6: Run a small prototype batch first
If the part is new or the vendor is new, don't start with 500 pieces. Start with one to five. This applies to CNC mechanical parts, machined housings, connectors, and anything with tight tolerances.
Use the prototype to test:
- Does the part fit the assembly?
- Does the finish match expectations?
- Did the supplier follow the drawing or 'improve' it without asking?
- How did they handle questions or issues?
The prototype isn't free, but it's cheap compared to a full production run of wrong parts. I've seen a $300 prototype save a $9,000 order. Simple.
Step 7: Confirm invoicing and compliance before production
In 2021, I found a great price from a new vendor—about 20% cheaper than our regular supplier. We ordered 150 CNC machined parts. They couldn't provide a proper invoice. Handwritten receipt only. Finance rejected the expense report, and I had to explain why our department budget was short $2,400.
Now I verify these before placing any order over $1,000:
- Can they issue a proper invoice with our PO number?
- Do they accept our payment terms or require prepayment?
- Are they registered to do business where required?
- Can they sign our NDA if the drawings are proprietary?
- Do they have insurance or quality certifications if the part is critical?
Per FTC advertising guidelines (ftc.gov), precision claims must be truthful and substantiated. That goes for suppliers too. If they claim 'high precision' or 'aerospace-grade,' ask for inspection reports, not just marketing language.
Step 8: Keep a primary and a backup
Part of me wants to consolidate everything to one vendor for simplicity. Another part knows that redundancy saved us during the last supply chain crunch. In our 2024 vendor consolidation project, I tried to cut from nine vendors to five. I got to seven. I compromise with a primary vendor and a backup for critical parts.
For aluminum machining service and CNC machined products, I keep two shops that have both passed the prototype test. For connectors, I have one domestic source and one overseas source. For stainless steel forgings, I don't keep a backup unless the volume justifies it—but I know who I'd call.
This isn't about distrust. It's about lead times. When one shop goes down, you don't want to be starting from zero.
Common mistakes I've made or seen
Even with a checklist, things slip. Here are the ones that hurt most:
- Assuming the cheapest quote is the cheapest total. Add setup, shipping, inspection, and revision costs before you compare.
- Skipping the thread standard on connectors. A brass hose connector female with the wrong thread is scrap metal.
- Not asking who pays for rework. If the supplier makes a bad part, who eats the cost? Get it in writing.
- Treating a fast quote as a complete quote. Online platforms like Oshcut are great for speed, but you still need to verify specs, certs, and tolerances.
- Letting a vendor 'improve' the design without approval. I've had a shop chamfer an edge that didn't need it. It looked fine. It also didn't fit.
I have mixed feelings about how much process is enough. Too little, and you get burned. Too much, and you slow down engineering. My rule is: use the checklist for any part that touches a customer, a fluid, or a safety system. For internal brackets, you can lighten up.
That said, the checklist isn't a substitute for engineering review. I'm a purchasing admin, not a machinist. My job is to make sure the right questions get asked before money changes hands. When I do that, the specialists can do what they're good at—and I don't have to explain a failed expense report to finance.