Commercial Equipment & Machinery

Three Practices for Smoother Commercial Equipment Rollouts

TriMark USA's Bryan Musgrove outlines site playbooks, lead-time scheduling and consolidated packaging for multi-location equipment deployments.

Sora MiyaharaNovember 1, 20265 min read7 views

Stainless-steel kitchen equipment, including toasters and a holding cabinet, arranged beside stacked crates, pans and a planning wall in a conceptual illustration.

Rolling out new equipment to support a menu launch involves far more work behind the scenes than the item that eventually reaches the plate, according to Bryan Musgrove, divisional senior director of national accounts at TriMark USA. In an outline of lessons from past rollouts, Musgrove described three practices intended to make deployments smoother across a brand's locations.

Build a location-by-location playbook

Musgrove said the first step is a playbook that maps how each site will handle the new equipment. TriMark worked with a brand that needed new toasters to add toasted sandwiches to a breakfast lineup already built around biscuits and wraps. Site conditions varied: some locations had electrical capacity that was already maxed out, while small mall or urban sites lacked the counter space for a toaster. In those cases, space had to be created by adding shelving or an additional table, which in turn affected workflow.

The playbook, he said, separates locations that are plug-and-play from those that require additional support.

Schedule around the manufacturer's lead time

Timing should be built from what the equipment maker can actually deliver. Musgrove noted that a manufacturer might be able to produce 200 units, but the question is how long that takes; at 10 units a week, the order would take 20 weeks. In other cases, a supplier may have inventory to cover the first 50 units, then need to order parts from overseas—an eight-week step before the remainder can be completed.

For items launching alongside a marketing campaign tied to a specific season or occasion, Musgrove advised working backward from the target launch date to set an achievable timeline.

Consolidate packaging to simplify deliveries

Smaller wares do not have to ship to each location in their original boxes. Musgrove suggested asking the dealer to consolidate and repackage items into a single package per location. TriMark did this for a brand adding macaroni and cheese to its sides, an addition that required visual holding cabinets, pans and serving scoops in varying sizes. The items were combined into one package per site, along with instructional materials and exterior labeling so managers knew exactly what they were receiving on arrival.

Musgrove framed the three steps—deciding which locations need more support, planning to the manufacturer's lead time and simplifying deliveries—as a way to keep a rollout on track. Done well, he said, the launch can generate buzz for the new item and increase traffic.